Hello everyone:I have been working with the SDK in the P6 version 8.3, and I interacted without problems between the database and the SDK spreadsheets. After to upgrade to version 8.3.15 the spreadsheet Activity6v6.xls works partially: every time I try "Set Activity Relationships", I get the following error: "Row 3: Insert new TASKPRED: Values are required for lag_hr_cnt" for each of the activities that the project has. I have verified with previous projects where I have entered this information without problems and it gives me the same result, so I conclude that it is due to the upgrade made. Does anyone have any ideas? Thanks alexander
P6 SDK: Activity6v6.xls work partially after to upgrade Primavera P6 8.3 to 8.3.15
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Hi Mohammed Ali,
I sent you the verification code, please send me the product key. Mi email is [email protected]
Thanks
alexander
For all planners who are still using the 4 sdk files:
The activity file <ACTIVITY6v83.xls>
The project file <PROJECTv83.xls>
The dictionary file <Dictionary6v7.xls>
The WBS file. <WBS6v6.xls>
you can try this tool http://www.mediafire.com/file/ougb7bfikqdae9n/PM_Advanced.xlsm/file
where this video explains exactly how you can use it https://youtu.be/YjVqyzOCgSE
no problem
Hello Mr Zoltan
I think there is a misunderstanding from my side.
I apologize and thank you for all of your efforts and time in this forum.
The file that can be used instead of <activity.xls P6 R8.1>
That is what you wrote:
<<<I have another spreadsheet that DOES NOT require SDK and can be used with any version
if so tell me what you email address is and I wil send it to you. >>>
send you what ?
Hello Mr Zoltan
Please send me a copy from this file.
This is my email address: [email protected]
Thank you in advance.
its a 2 step process
1st import the activities then import the relationships DO NOT do both together because if the relationship that you are referencing is toward the bottom of the activity list it wil not have been imported yet so it cant find it to make the relationship.
Start with the Rawdata tab and populate that tab
then go to the Main tab and create the activities then select Fill Activity Sheet
then select Fill Activiy Relationship Sheet
then save the file
import activities into P6
then import relationships into P6
in the Rawdata tab in the relationship column is you have more than one predecessor relationship you can add a comma afte rthe 1st relationship and put in the 2nd relationship\
ie 1005,1010 FS,SS
Hi Zoltan,
With the activity6v83.xls spreadsheet received and tried to work directly with the "Set Activity Relationships" option, getting the same error: "insert new TASKPRED ..."; but with the last sample file that you also sent me, I have been able to solve this problem by loading the relationship of the activities through the option to import into Primavera P6. Is it right?
Regards,
sent
Hi, my email: [email protected]
thanks a lot and best regards
tell me what you email address is and I will send it to you.
you need the newer spreadsheet for version 8.2
if you just want to add activites lisiitng the
activity id, wbs, original duration, remaining duration, activity name, predecessor ID #, realtion type and lag
I have another spreadsheet that DOES NOT require SDK and can be used with any version
if so tell me what you email address is and I wil send it to you.