Cumulative S-curves:

D
David Mason 👤 Member for 7 years 10 months

Seemingly (without defaulting to Excel) we STILL can't generate in P6 Early and Late cumulative progress curves which form a natural continuum (at the data date) from the cumulate Actual progress curve !

Or am I missing something ??

R
Rafael Davila 👤 Member for 22 years 3 months

You replied - Thanks Rafael - we don't have these report generators..... are they options in P6 or an external package ?

  • These are options on other software, among them old P3 software, I expect similar options to be available in P6 as these reports have been required for decades.

If your software cannot generate with ease such S-Curves as it should you might try external packages sych as Project Tracker.  Based on what their brochure says I would expect Current and Baseline Early and Late S curves be available.

Project_Tracker_More_S_Curves

Z
Zoltan Palffy 👤 Member for 16 years 10 months

filter for what you want then selecy select view show on bottom then select activity usage profile

then right click on the lower right graph area and select activity usage profile options

from here you can select either costs or units to be diaplayed as well as the baseline and or the current schedule

 

[[wysiwyg_imageupload:5856:]]

D
David Mason 👤 Member for 7 years 10 months

Thanks Rafael - we don't have these report generators..... are they options in P6 or an external package ?

The only one i can dig up is teh "Resource Usage Profile Options" which allows the stacked histogram and a default overall planned curve :(

  

R
Rafael Davila 👤 Member for 22 years 3 months

This is how ancient P3 would give you the Early and Late Cumulative "S" Curves for current plus two target/baselines.

 

SCurve01

This is how Spider Project would give you the S Early and Late Curves for current plus two baselines named baseline and compared schedules.

SCurve02

I do not use P6 but it shall be as easy as 1,2,3, so easy, no big deal.

D
David Mason 👤 Member for 7 years 10 months

These are the only curves P6 offers.....

Baseline

Budgeted

Actual

Remaining Early

Remaining late

Planned Earned Value

Earned Value

Estiamte at Completion.

 

Where do you source the Baseline Early and Late from please ??

R
Rafael Davila 👤 Member for 22 years 3 months

As soon as there is progress and the DD is moved then for current updated schedule actual Early and actual Late S Curves will overlap to the left of DD giving you the impression it is a single line. Then after the current DD they will separate showing current plan early and late cumulative S Curves.  Try setting your diagram to show both Early and Late cumulative S Curves and nothing else.  

If you select to display remaining S Curves, only remaining values at DD will be considered and it will be 0 at DD.  It will not accumulate whatever is at the left of the DD.  Try setting your diagram to show both Early Remaining and Late Remaining cumulative S Curves and nothing else.

You can add to the diagram the original plan Early and Late S curves.

Now try showing all at the same time.

Good Luck

R
Raymund de Laza 👤 Member for 16 years 6 months

To obtain the required curve, Actual Values shall equate with Earned Values and the Remaining Values shall be the difference between At Completion and Actual Values.

D
David Mason 👤 Member for 7 years 10 months

Yes - that's what I want them it to do (but the remaining curves start from zero again at the data date).

If P6 could hold the Early & Late cumulative curves at the baseline - this would give an envelope between the early and late curves which the actual progress curve could be measured against. But P6 doesn't offer this yet and defaulting to Excel as usual :( 

R
Raymund de Laza 👤 Member for 16 years 6 months

Early Remaining or Late Remaining Curves shall originate from the End of the Actual Values at Data Date. The Curve shall be Continues until At Completion Values.

Z
Zoltan Palffy 👤 Member for 16 years 10 months

progress based on what dollars, manhours or units ? What is your measuing stick ?

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts