Resource problem

A
adab azeez 👤 Member for 9 years 10 months

Hi mates.
I am working on 18 hours calender, 2 Shifts (9hrs X2).
I have been asked to use 10 riggers over all.
So what would be our maximum units per time and default units per time.

Z
Zoltan Palffy 👤 Member for 16 years 10 months

either 5 or 10 depeneding on how you set up your calendars and shifts 

R
Rafael Davila 👤 Member for 22 years 3 months

But at times the crew composition of different shifts working on same activity is different, also it might also be desirable for shifts to have some overlap.  Easy if modeling different teams working independent of each other [at different hours] on same activity. 

2_Shifts10_Riggers

It is Volume of Work and Productivity [production rates ] what gives meaning to activity durations.

Riggers_Volume_Of_Work

If start of activity is delayed for latter on same day the work done by the different shifts is re-distributed and activity duration changes, therfore it is not a good idea to split the activity into two. 

SW0023

To make is easier to visualize say: 

  • Crew 1 shift 1 works on Monday, Tuesday, Wednesday and can do 50% of work per day.
  • Crew 2 shift 2 works on Thursdays and Fridays and can do 100% of work per day.  
  • Easier, no overlapping, shift work on different days .
  • If activity stars on Monday it will take 2 days, if activity is delayed to start on Thursday it will take one day.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts