Hi mates.
I am working on 18 hours calender, 2 Shifts (9hrs X2).
I have been asked to use 10 riggers over all.
So what would be our maximum units per time and default units per time.
Resource problem
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
either 5 or 10 depeneding on how you set up your calendars and shifts
But at times the crew composition of different shifts working on same activity is different, also it might also be desirable for shifts to have some overlap. Easy if modeling different teams working independent of each other [at different hours] on same activity.
It is Volume of Work and Productivity [production rates ] what gives meaning to activity durations.
If start of activity is delayed for latter on same day the work done by the different shifts is re-distributed and activity duration changes, therfore it is not a good idea to split the activity into two.
To make is easier to visualize say: