Greeting to all.
Whenever I am adding a new resource to any activity in p6, the budgete units of all previously added resources are automatically changing. It drives me really crazy to put recorrect the budgeted value again and again.Can anyone advice why it is happening and how to prevent.
Thanks in advance.
Resource Budgeted Units
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Thank you so much david
Under Edit, User Preferences, Calculations:
Chose "preserve" rather than "recalculate"