XER Import Error - Changing Version Not Working

When attempting to import an XER from a new version of P6 to the 8.4 version I have, I get an error stating, "The import file is invalid."

I have already changed the version number in notepad. This trick only works sometimes when I import files from new versions of P6. I would ask the scheduler to send a saved down version of the file but our GCs aren't always accomodating. Are there any other tricks I can try when this occurs? 

 

UPDATE: I was not able to resolve this issue. However, by the mercy of my IT department, I was able to get an updated version of P6.

S
Santosh Bhat 👤 Member for 21 years 1 month

Make sure you aren't introducing any more or less spaces when you replace the Release number with 8.4

This can be a reason why modifying the XER fails

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts