Hi all,
Using P6 Professional R16.2, I can't find the administration functionality to add a new Resource "Unit of Measure".
Thank you in advance for the help/assistance.
Cheers,
Arman
Hi all,
Using P6 Professional R16.2, I can't find the administration functionality to add a new Resource "Unit of Measure".
Thank you in advance for the help/assistance.
Cheers,
Arman
Hi David,
Thanks for that, very much appreciated. I did find the Unit of Measure in the EPPM Database under Administer pull down menu, then Enterprise Data. However, it seemed I have no authority to add a new unit of measure. I will just talk to our Administrator.
Many thanks again.
Regards,
Arman
Unit of measure for material resorces is managed in the Web client if you have an EPPM database. If you have a PPM database, then it isin the admin pull down under categories