Primavera P6 and Assigning Individual Labor Resources to Roles
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
In the schedule consisting of thousands activities these procedures are very time consuming. When resources are limited the schedule with roles instead of resources is not feasible. Initial resource assignments may become not optimal very soon when execution differs from planned (it happens all the time). And this time consuming procedure shall be repeated again and again. Is it practical?