Hello ya'll,
I have a filter on my planning so I only see the items of my discipline. In none of the heading bars I can see the
correct summary of the items shown in my chosen layout.
Now I copy them to Excel so I can select the items I need to know.. But this doesn't work efficiently..
Anyone has the answer?
Thanks! Mi
Try adding a UDF number field, enter "1" as value to your filtered results. Your grouping band should show the count (sum) of activities in your grouping.
how do u copy them ? highlight then then right click copy to excel ?