How can we show multiple basines on barchart area? and up to how many baselines can we show, in addition (under) each actual bar?
How to show multiple baselines on bar chart area
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
u can show 3
1st go to project maintain baseline then choose it
then go to assign baseline and select the one that you just chose to maintain.
Do this for the Primary baseline
the Secondary basline
and the Tertiary baseline
then go to bars and check the box next to each of these descriptions
make sure to put each of these bars on a seperate row or they could be show on top of each other