Hi,
I have certain admin rights where I can create / edit the EPS. One of my schedulers can only see the EPS nodes that she has her projects under. She has 3 nodes, however, they are not showing in the same order as in the EPS structure. Is this something to do with her layout or user preferences ? I have had this before and cant remember how to fix it.
Any help would be appreciated.
Regards
Scott
Yes tried using a default layout and still the same. I am just waiting on pemission to gain admin rights and I will then investigate more.
Thanks for your reply.
If you mean the user_setting is corrupted and this resulted in the problem with the layout, you can reset user setting by login to your database and issuing the following command:
update userdata set user_data = ‘null’ where topic_name = ‘pm_settings’;
this will reset user setting back to default setting. I doubt this is the issue as this doesn't reset the layouts. But it worths the shot.
Another option is to delete the user and add a new user as the new user recieves default setting.
Did you try to use one of the default layouts in P6 to see if the problem resolves? The issue might be the corrupted user layout that sometimes happens and only workaround is to built it from scratch.
The WBS corruption is not a usual suspect as normally WBS corruption returns error or makes project invisible.
then check the admin rights
Thanks Guy's but Id already tried these along with sharing my layout and neither worked. I think it is something to do with user / admin rights.
Go to View > Group and Sort By >
Uncheck the "Sort bands alphabetically"
uncheck hide when empty in your grouping