Calendar 28/28 or 5wks/2wks

Has anyone ever created a 28days work and 28 days off calendar or 5 weeks on and 2 weeks off calendar?

If yes, please give me some pointers....................thanks

All constructive assistance welcomed..............no jokers

R
Rafael Davila 👤 Member for 22 years 3 months

Insane, recurring calendar exceptions are so common that even free e-mail & calendaring software provides for easy handling of recurring events. 

CE04

By the same token other scheduling software also provide for easy handling of recurrent calendar exceptions. It is not uncommon for named resources to have their own calendar exceptions even if they share other exceptions such as holidays.

CE02

CE03

Maybe if using Excel and transfering the data to any P6 calendar you can do it.  Being so common this issue it is not a joke but a very serious one. It is hard to believe there is no easier way.

In the case you are modeling rain days across several calendars even when not recurrent, adjusting these individually for each calendar can be a nightmare when it can be so easy if editing/deleting the particular calendar exception.

CE06

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts