Hello Everybody
I have a problem. I dealing with Resource usage spread sheet in P6. The problem is my time duration of Budgeted Units and actual units are not matching. Dates of activity are 1.March.2017 to 19.Jun.2017. Actual Units are showing in this time duration but budgeted Units start from Jun.2017 to July.2017. I need these budgeted Units to start from 1.March.2017 to 19.Jun.2017. Kindly help me.
make sure that the resources on are the same calendar as the activities are