Dear Planners,

 

I have tried to delete a project and this is unfortunately going to show a command as of "Other users currently have the project......open.You may not delete this project"

 

Best

osfattt 

Z
Zoltan Palffy 👤 Member for 16 years 11 months

either someone eles is in it 

or

it has been checked out 

or

the program shut down unexpectedily while it was open and it thinks that it is still open

also when you leave p6 always select file close all 