Percent Complete Type-Duration Type

I have been looking around for a good explanation on the percent complete type and duration type settings. I have a pretty good idea about how they work and when to assign what, but would love to have a direct explanation from someone who actually worked with them.

 

Thanks in advance,

 

Mike  

Z
Zoltan Palffy 👤 Member for 16 years 11 months

if you want to use earned value you have to use for percent complete however this does not update the remaining duration or your actual units so you can run a global change

where physcial % complete is greater than 0

then duration % complete = physical % complete

 

for duration type if you do not want you labor units determining your durations use fixed duration and units/time

if you want your durations determined by the resource then use fixed duration & units

Forum Sponsor

Top Posters

sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts