New resources & price/unit while importing project.

K
Kannan CP 👤 Member for 18 years

Hi all,

I have a Project with resources(100 nos) and price/units. I export it and send to the Contractor. Contractor added few resources (now 105 nos) and also he changed the price/unit of certain existing resources.

Then while importing it to my system (creating as new project), what changes to be expected, if the default option of "Keep existing" for resources is selected.

1. The existing resource pool in my system will be added by the additional 5 nos (added by the Contractor)?

2. The price/unit of the above said certain resources in my existing resource pool wil be updated?  

 

In my understanding, if we use "Insert New" option for resources while updating, the existing 100 resources remains there, and a new set of 105 resources will be created with the respective price/unit. This will make the resource assignment area bulky.

Another question: If I delete a project, the related resources also will be deleted? The resources are not shared with another project.

Best Regards

Kannan

K
Kannan CP 👤 Member for 18 years

Hi Zoltan,

by using the UPDATE EXISTING option, how abt the new 5 resources added by the Contractor? It will be added to the existing resource pool of my original schedule?

Thanks

Best Regards

Kannan

Forum Sponsor

Top Posters

sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts