GreetingS to All.
in My project most of the WBS do not show schedule % complete, but in that WBS, All activities are showing SChedule% complete as well as Performance % complete ?
What Could be the possible reason ?
Please suggest.
Thanks in Advance.
schedule % complete is based on work not costs. The schedule % Complete specifies how much of the activity's baseline duration has been completed so far. Computation is based on where the current data date falls between the activity's baseline start and finish dates. The Schedule% Complete indicates how much of the activity duration should be currently completed.
once again you are mixing apples and oranges this has NOTHING I repeat NOTHING to do with costs
With Respect,Thanks Zoltan Palffy and Kannan CP.
Some of the activities which do not have budgeted cost, still showing SChedule % complete.
Adab,
To find out how schedule % complete is calculated, show the Schedule % complete value in the columns area, and then under the "view" main menu option in the Windows client, select "hint help".
Now when you hover over any column heading, it will display how the column is calculated....
How the schedule% is calculated for the activities without any cost.
If you assign a baseline to the project, the schedule % may show 100% to an activity , due to the delay of that activity.
nope just what I wrote
Zoltan,
I believe it also depends on the time frame.
Regards
Kannan
It will ALWAYS be calculated as (BCWS• 100) / BAC
(budgeted cost for work scheduled times 100) divided by Budget at Completion
if you do not have cost in your schedule then 0 divided by anything is 0
Is any budgeted units assigned to the activities?
Regards
Kannan