Dear All,
I'm preparing the schedule by system, using activity code. there are thousands of system and subsystem, are there any quick way to import/export the activity code from excel.
thanks
Dear All,
I'm preparing the schedule by system, using activity code. there are thousands of system and subsystem, are there any quick way to import/export the activity code from excel.
thanks
this is a 2 step process
step 1 is buildign the activity code dictionary. The fastest way to build this is by using SDK
step 2 is populating the activites with the proper code value. The fastes way to do this is to export all of the activities along with the code fields and then populate the code value fields in excel and import the excel file back into p6
OR XERfileparser
However if you want to transfer activity codes from a project to another you can use update baseline function in P6
Use SDK