Hello Everyone,
Please i need an urgent assitance, in my activites table My Start are finish milestones are not showing, Including my Project start and finish date, Has anyone come across this before?
Please i need an assistance on how to fix it
Thanks in anticipation
I get this all of the time. My milestones are gone or all of my activities are gone. No it just a filter being applied.
Thanks Alot
filter for all