Replace Resource without change in Budget Units / Time

How do I replace a Resource without change in Budget Unit / Time either by using the "Replace" function or "Global Change"?

C
Clement Mario 👤 Member for 9 years 8 months

Zoltan Palffy,

Thank you for the suggestion, will give it a try and update you.

Z
Zoltan Palffy 👤 Member for 16 years 11 months

you would have to ADD another resouce then run a global change to make them equal then delete the original resource 