Please help!!
In my cost loaded program the Performance and Schedule % complete are showing as 0% at all WBS Levels but budgeted and actual costs are displayed.
Morever, when i further collapse the program to the activity level, the performance % complete is being shown but the schedule % complete is still being displayed as 0% for the activity.
Please explain how to track the schedule and performance % complete at WBS level too.
you can not roll this up at wbs level this is by design becasue there are 3 different types of % complete that you can choose whoch are "Duration", "Units", or "Physical. So if some activites were duration % complete and some were units % complete and some were physical % compelte then you would have apples,, oranges & pears.
If you want to use WBS Level % Complete then you can use steps
The percent complete using the WBS Milestones that are assigned to a WBS level. Computed as Actual Weight of Completed Milestones divided by the Total Possible Weight of All Milestones.