Hi all,
Is there a way to convert Activity Codes to WBS in P6. I have searched and some people suggested to use SDK. First i dont know what SDK is and i dont have that too?
I would appreciate if anyone could suggest the easiest way to convert.
Thanks,
Naveed
open the excel file dictionary6s.xls
type in the password
select update project list
then select your project
then select GET Activity Codes
now copy these codes
now open the wbs.xls file
and type in the password
select update project list
then select your project
then select GET WBS
now copy the codes from the other spreadsheet into the wbs spredshsheet
now in the wbs spreadsheet select SET WBS
done
Someone can more detail explain for us how to use SDK to convert Activities code to WBS.
Thank you so much
p/s: Video is better :D
you install sdk then you use the excel spreadsheet. Then sdk bridges the gap or is the interface between the spreadsheet and P6.
So in the spreadsheet you can select your project and you have the get button and the set button
the get button is like export in p6 and the set button is like the import function in p6
so you use the get button to export your info from p6 change it or populate it then you select set to import it back into p6
you can do this for several different categories.
Thanks Zoltan,
Can you further explain how i can use that in my perticular case?
Thanks
sdk stands for software development kit this come with p6. Almost every program as a sdk that they make available to developers of other software in this case sdk will be used inconjunction with excel.