Resource limits changing during levelling

A colleage is levelling a joint schedule.

Some labor resource limits are changing while levelling - randomly

It looks to be a calendar issue within his user profile (max units/time are changing by a factor of 24).

Any idea, what would be the cause? 

 

 

 