Collapsing and Expanding Sub Projects

E
Emma Lang 👤 Member for 9 years 9 months

I'm trying to collapse some but not all of the sub projects I have. Group and sort does it to a certain level, but is there a quick way to select a number of sub projects and expand or collapse them without having to affect the whole schedule?

 

Thanks

Z
Zoltan Palffy 👤 Member for 16 years 10 months

ou have 2 options

option #1

you can filter your projects that you want to collapse and expand 

 

option #2 

you can create a Project Portfolio and put the projects in there that you want to collapse and expand