Hi all,
I wonder if you can help. The schedule i'm building below has some original durations that differ from the longest 'At Completion Units' and some that match - I am under the impression that the planned (original) duration of a task should be equal to the longest resource 'At Completion Unit' of that task. All calendars are the same - any ideas?
i don't see how one thing has to do with the other one is units and one is duration totally independent
Thanks David - apologies for the multi-post. I blame my P6 trainer all those years ago at ACS ;) haha!
Hmm. "At completion units" is the total resource quanity, forecast or actual, at the finish of an activity. Original Duration is a measure of time. I picture duration as belongng to an Activity's "x" axis, and units as the "y" axis......
Also note that "SAVE" at the bottom of this dialogue is actuallt "POST" !!