Original Duration vs At Completion Units

Hi all,

 

I wonder if you can help.  The schedule i'm building below has some original durations that differ from the longest 'At Completion Units' and some that match - I am under the impression that the planned (original) duration of a task should be equal to the longest resource 'At Completion Unit' of that task. All calendars are the same  - any ideas?