Using Primavera to Track Parking Availability

C
C L 👤 Member for 10 years

We have a project with a requirement to maintain x number of parking spaces throughout.  There are many activities that add and remove parking spaces.

I have found that in Layout: Activity Resource Assignments I can sort of get a spreadsheet showing the daily parking counts, but there are exceptions.

The goal is a printout with a gannt chart schedule above, and a total of the available parking spaces below.  Is this possible?

I started with a simple schedule, and added LOE activities to create activities to assign the baseline quantities of spaces we started with.   I defined the parking spaces as a resource.  For each activity, in the Units/time field, I inserted either the number of spaces the activity adds or removes.  In the Project/Resource Assignments view (which I have never previously used), I found the finish dates for the activies are very different than on the Project/Activities view, which  causes the total number of spaces at any point in time to be incorrect.

Any direction on the best way to go about this, or links on documents to read would be greatly appreciated.

I am using Primavera Contractor, which as we understand is P6 limited to 2k activities.

C
C L 👤 Member for 10 years

Thank you for the responses.  Peaks and troughs won't work - I need to report actual spaces available on a daily basis (and hopefully weekly) basis.

I think I have figured this out with the following, BUT

1.Dictionary/Resource and adding Parking as a Material resoure

2.Start with Activities that define the current parking quantities.  For each activity, under units/time put in how many spaces there are in each area by putting in the spaces/day

3. For construction activities, enter how many spaces each activity adds or removes during it's duration, defined in the resource as space/day

4. View/Show on Bottom/ Resource Usage Spreadsheet, showing my Timescale in days.  It shows the daily spaces from the data date forward.  However , I have the following problems:

a. It only shows data from the data date forward; no past numbers.  I would like to be able to show the client they had the total number of required spaces last week, etc. Is there a way to do this?

b. It shows both LOE and Task Dependent activity resources, and both positive and negative resouces in the table. However, for Task Dependent Activities that are not on the critical path, it only shows the resource for a short time (I think the duration less the float).  This seems to be based on an incorrect total amount of the resource it is calculating in the Activity Detail, and I have no idea why.  I need it to show the same quantity of resources /# of spaces for each activity for the duration of that activity.  For now I'm only putting resources on LOE or critical activities.  But I need to address this so it still works as progress changes activities from critical to non critical & vice versa.  Is there any other way to address this other than creating extra LOE activities that only measure quantity of parking?

bb. If I change the logic of an LOE activity, the activity finish date changes properly.  However the Resource finish date does not recalculate.  Is this what the option to "Level Resources" would do, so basically I cannot track parking in Contractor? or is this a totally different problem as described in this post:

http://www.planningplanet.com/forums/primavera-version-pm5-pm6/421633/r…

Would MS project allow me to do?  If there is a way around this, the remainder of the challenges are:

c. Is there some way to show in the Gannt view, the "units/time" for each activity - ie the number of spaces assigned to each activity?  For now I have put the quantity in the Activity name, but the field exists - I would like to display it in the Gannt view.

d. The way I defined the resource per 1 above lets me add sub resources.  So I could do an overall Parking resource, that has subresources of deck parking and surface parking, and further define each by Deck A, Deck B, Surface lot 1, 2 etc. However, if I add the resources as one of these subresource, I cannot show the total parking in the resource use spreadsheet - it only shows one subresource at a time.  I think I must just be missing some sort of setting, but cannot figure it out.

e. I tried to address item d using resource codes, but that is apparently NOT any way to do this either....

f. I'm fairly certain there is an efficient way to do this in the program, but I would be more comfortable with a better understanding of how the program treats non labor resources - budgeted, Unit/time, remaining, etc.  Can anyone direct me to a site or article that explains this?

g. To show the correct data on a printout, from the Resource Usage Spreadsheet, I right click and select "Remaining Units." If I select Actual I get blanks, and if I select budgeted only the critical items have data.  So I think this has something to do with all of the above, and that I'm not quite doint this correct...

Z
Zoltan Palffy 👤 Member for 16 years 11 months

if you use LOE and a resource it wil stack your all of your resource on the start date unless you use a curve. You can create a striaght line curve for even distribution.

But I would assign the reosurce to the actual activity then select view show on bottom resource useage spreadsheet

M
Mike Testro 👤 Member for 20 years 6 months

Hi C L - Welcome to planning planet.

Primavera Contractor loses many P6 features and will probably not perform the way you wish.

You have set up a "Parking" resource for the tasks that need it and a simple histogram display should show the peaks and troughs.

First check that the calendar for your Parking resource is the same as the schedule calendar which could be the cause of the problem.

I doubt if Contractor has a resource levelling feature so you will have to manually adjust your logic to even out the histogram.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts