Editing Float

Please someone help me..

I have been creating a baseline for a high rise building project(Contract period is 2 years).I found that many activties have more than 200 days float and some activties have -1 (Minus one day) float. Although project completion date has come to correct finishng date.

Please someone help me as soon as possible by telling advice to reduce the float(Contract document indicates as maximum allowable float is 60 days)

T
Tom Boyle 👤 Member for 19 years 6 months

Agreeing with Zoltan.

To reduce float, assign a later predecessor and/or an earlier successor.  No need to be more specific, since whoever wrote the specification doesn't really CARE about your sequential plan to accomplish the work.  I suppose he'll get what he's after.

Mike's advice to avoid dangling finishes is definitely good, though I would not expect that to contribute to the problem of excessive float in a baseline project schedule (assuming no progress).

Finally, the small negative float (-1d) could have several causes, but I would first look for a small clock-time mismatch at the project completion milestone (e.g. finishing at end of day when the project must finish by constraint is set to beginning of day.) Alternately, there could be a late constraint somewhere that you don't know about. 

M
Mike Testro 👤 Member for 20 years 6 months

Hi Mohamed

This happens when you use SS logic with Lead Lags and no end successor.

As Zoltan says make sure every task has an end successor even if it down to Project Completion.

Best regards

Mike Testro

Z
Zoltan Palffy 👤 Member for 16 years 11 months

it all depends on the level of detail in your schedule. can you tie this to punchlist, commissioning or testing or something other than the proect finish milestone.

 

Another thing to do it to add an additionla predecessor whch is later in time. 

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts