Unable to configure P6 EPPM database with P6 Client.

M
maddy jais 👤 Member for 11 years 2 months

Hi,

 

Can you please explain how to configure P6 EPPM database schema with P6 client as im not able to configure same db instance in P6 client.Its saying you cant configure EEPM database in P6 Professional.

Z
Zoltan Palffy 👤 Member for 16 years 11 months

go to 'All Programs'' --> 'Microsoft SQL Server' --> 'Configuration Tools' --> 'SQL Server Configuration Manager'

SQL Server Config Mngr window will open.

In the right hand site of the window you will see different data bases. Right Click on the SQL Server 'Primavera' and click 'start'.

Then try again to log in in Primavera