Hi,
I applied a filter on the Activities pane then went on the Resource Assignment pane, applied the same filter and came up with the same start and finish dates on the summary, but different Original Duration.
My question is, what are the possible reasons for that?! And is there a solution to show the same Original Duration?!
Regards,
Wadi El-Din Hammouda