Dear Sirs,
please note that i have for example project w/2 WBS:
- WBS #1 weight = 75% of the ABC Project
Included 2 activities
act #A weight = 60% of WBS #1
act #B weight = 40% of WBS #1
- WBS #2 weight = 25% of the project
Included 2 activities
act #C weight = 35% of WBS #2
act #D weight = 65% of WBS #2
I need this data appears as follows in the schedule as activities weights not activities steps weights:
Activity ID Activity Name
Weight
ABC Project
100%
WBS #1
75%
10 Act #A
60%
20 Act #B
40%
WBS #2
25%
30 Act#C
35%
40 Act#D
65%
regarding that i will use the above in updating progress.
please clarify in clear steps and snapshots if available.
best regards
Abeer