Activities Weights

Dear Sirs,

please note that i have for example project w/2 WBS:

  • WBS #1 weight = 75% of the ABC Project

Included 2 activities

act #A weight = 60% of WBS #1

act #B weight = 40% of WBS #1

  • WBS #2 weight = 25% of the project

Included 2 activities

act #C weight = 35% of WBS #2

act #D weight = 65% of WBS #2

I need this data appears as follows in the schedule as activities weights not activities steps weights:

Activity ID             Activity Name
 
Weight

ABC Project
 
100%

WBS #1
 
75%

10                     Act #A
 
60%

20                     Act #B
 
40%

WBS #2
 
25%

30                     Act#C                          
 

35%

40                 Act#D                              
 65%
 

regarding that i will use the above in updating progress.

please clarify in clear steps and snapshots if available.

best regards

Abeer

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts