Hi everyone,
Right now I’m doing a contract migration from Lump-sum to Time & Material, I updated my schedule once a week but now my client need the number of hours expended by day.
Throw the Activity Spreadsheet Usage I can found all the information but when I update an activity by hours Primavera P6 share out the hours number along all task duration.
I’m wondering if Primavera P6 V8.2 can keep the hours number entry an specific day even if the task continue for two or more days
Example: Activity A (5 days)
Spent hours
Primavera P6 V8.2
I want
Monday
5h
4.2h
5h
Tuesday
3h
4.2h
3h
Wednesday
4h
4.2h
4h
Thursday
2h
4.2h
2h
Friday
7h
4.2h
7h
Thanks for your help.
Use bucket planning
by default Primavera spreads your manhours linerarly over the activity. To do what you want first make a cumstom curve then assign the custom curve to the resourses where you want this to happen.
go to enterprise then resource curves
then select ADD
Then name it what you want
Then Select Modify
now for the curve values enter these values these values go across the bottom on the curve
0.0 0%
6.0 5%
6.0 10%
6.0 15%
6.0 20%
3.5 25%
3.5 30%
3.5 35%
3.5 40%
4.8 45%
4.8 50%
4.8 55%
4.8 60%
2.5 65%
2.5 70%
2.5 75%
2.5 80%
8.2 85%
8.2 90%
8.2 95%
8.2 100%
now assign the curve to the resource