P6 Beginner Question - Can you delete same predecessor from multiple activities

S
sam dsoza 👤 Member for 19 years 11 months

Hello All,

So I am not new to P6 but have forgotten most of the skils for not having to use it.

My question as the subject line mentinos is if you could delete predecessor form multiple activities. Please advice.

 

Thanks

SD

Z
Zoltan Palffy 👤 Member for 16 years 10 months

within P6 you can only delete multiple predecessors from and activity but you can not delete the same predecessors from multiple activities.

You can do this with sdk and the associated spreadsheet.

EVERYTHING is based on the activity id not the predecessor id  