Original duration = budgeted labour unit

want to know why some times we are doing budgeted labour unit = original duration

Z
Zoltan Palffy 👤 Member for 16 years 10 months

by default the budget labor units equals the resources default units/time * original duration

therefore defaut units/time 8 hrs /day Times original duration of 5 days = 40 hours 