Hello Everyone,
Can someone advise how I run off a report of all the comments I have put in my notebook for the entire project?
Many thanks,
Diane
Hello Everyone,
Can someone advise how I run off a report of all the comments I have put in my notebook for the entire project?
Many thanks,
Diane
Create a new report with a Subject Area of only Activity Notebook. This will show only activities with notebook topics assigned.
go to reports on the right select add new report then in the wizard the subject area wil come up select Activity notebook
select next and then you can add your columsn and filters and grouping.