Importing Someone Elses P6 Native File (retaining all properties)

D
Diane Jones 👤 Member for 10 years 5 months

Hi all,

I am very new to P6 and need to update a colleagues programme that is off on long term sick after an operation and looking for some urgent assistance.

I have her native file (.XER) and need to import it onto my computer but when I do so the baseline that she has created does not show up?  I need to do a progress report on this programme and I'm stuck at the first hurdle trying to import it so it looks like hers.  If anyone can help it would be most appreciated.

Many thanks,

Diane

Z
Zoltan Palffy 👤 Member for 16 years 10 months

the baseline does not come with the xer see if you vcan get the baseline also

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts