Converting P3e 4.1 To P6

I'm looking for a way to convert P3e 4.1 data to P6, between Oracle databases. Exporting/ importing XER files is not an option because of the number and size of projects and other important features, such as number of Users, Layouts and Filters which cannot be exported via XER. This may require a hop to 5 then to 6. Any help or leads would be greatly appreciated!

D
Dieter Wambach 👤 Member for 19 years 4 months

Hi Bruce

In my opinion you'll have to go the hard way and use the upgrades of the database delivered by Oracle/ Primavera: 4.1 to 5.0, then 5.0 to 6.0, then 6.0 to 6.3? or 6.8 directly.

Don't forget the upgrade of your Oracle database if necessary.

Good luck!

Dieter

Z
Zoltan Palffy 👤 Member for 16 years 10 months

since exporting/importing is NOT an option then I think that the hop will be necessary 

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts