Trouble MSP XML import to 8.3.2

Hi all! 

Me and my team are running into some trouble when trying to import a XML file from MSP 2010, into P6 8.3.2 professional. 

Somehow, it looks like primavera is doing it's job, but when ready, the schedule is nowhere to be found in the EPS overview (no fitering on EPS). Then if you try again (without rebooting), primavera keeps kicking me out of the import options. 

Anyone else has had the same issue? 

thanks in advance!

Sander G.

S
Sander Gorissen 👤 Member for 19 years 9 months

Yes, Primaned found the solution!

Issue was in MS project with options-->Schedule-->Calendar options. MSP indicated 31 days per month ... Primavera can only handle 30 days a month ... 

Quick fix, if you did any research, thanks! 

Sander G.

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts