I have an issue with deleting one specific Global Calendar. When I check to see what project is using the Calendar, nothing shows up, and the same goes for resources. When I try to delete to calendar I get a message saying it cannot be deleted because it is being used by a project. My question is how do I find out what project (or baseline) is using the calendar whether it be the calendar itself or as a reference for the project specific calendar.
I am no good at report writing with P6 but if there is a report that would help, please do share with me.
Thank you for your time.
several ways to do this
1. add a column that shows you calendar
2. go to the projects directory make sure that you project is highlighted click on the defaults tab and on the lower right hand see what the default calendar is.
3. go to enterprise then click on a calendar and on the right hand side click on Used By
4. go to organize and group and group by calendar.
5. Same thing for the resources go to enterprise then click on a calendar and on the right hand side click on Used By but the click the resource button
https://www.planacademy.com/primavera-p6-calendars-biggest-problem/