Activities summary

Good day;

Iam working on a project "Tunnel" that is divided into Facilities, sectors and sections, where every sector consists of several sections and every section consists of different activities.

Iam trying to group & sort the activities per sector and not per section, for example:

Sector A: Section 1, Section 2

- Section 1 Activities: Excavation (start: 12 May 2016, Finish: 4 July 2016)

                            Concrete (Start: 13 June 2016, Finish: 12 August 2016)

- Section 2 Activities: Excavation (start: 3 June 2016, Finish: 4 August 2016)

                            Concrete (Start: 5 July 2016, Finish: 2 September 2016)

 

The question is how can I sort the activities per sector as follows:

Sector A Activities: Excavation (start: 12 May 2016, Finish: 4 August 2016)

                          Concrete (Start: 13 June 2016, Finish: 5 July 2016)

 

Thank you

I
Ibrahim Salloum 👤 Member for 10 years 5 months

Thank you Zoltan;

It worked, where I used the group and sort till level 4 (Sector) and added the process code at level 5 (Section).

Thank you.

Z
Zoltan Palffy 👤 Member for 16 years 10 months

I am assuming that these are codes and not a wbs

go to view group and sort 

select add

then under Group by select Sector (Do not check Indent)

and if you want the activities sort by start date either click on top of the column or under group and sort on the right select sort then select in the field name select start

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts