Hello,
I have created a few reports that i need to generate weekly at certain times ( after the weeks schedule has finalised and also at the end of a week when all schedule updates have been entered ). These also need to be generated at specific times of the day, is this possibble to set up in P6 V.7
Thank you
yes this can be done through the Tools Job Services utility. Using the Job Services you can tell it to Apply Actuals, Batch Reports, Export, Schedule, or Summarize.