Actual labor units in activity usage spreadsheet

Good Day P6 Users,

I have a project which started in March and I just completed October update.

I am copying units from activity usage spreadsheet to Excel to create a graph and I noticed that actual units distribution varies when I do some modifications on remaining activities without changing the data date.

I am wondering why are actual units changing even for march period ?

Does anyone have an explanation ?

Thank you.

Jean

R
Raymund de Laza 👤 Member for 16 years 6 months

Jean,

Suggestions:

1. In Resource detail, Uncheck the "Auto Compute Actuals"

2. In Activity Details, Use a "Fixed Duration & Units" for Duration Type.

 

Hope this will help.

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts