How to measure progress % in Manhour

R
Rehan Ahmed 👤 Member for 10 years 7 months

How to measure progress % in Manhour

Z
Zoltan Palffy 👤 Member for 16 years 10 months

thats a very general question 

answer #1

you have 100 manhours you are 50% complete you have earned 50 manhours even if it actually took you 200 manhours to get to 50% complete you still have only earned 50 manhours. 

or you can say I have 100 manhours budeted and I need 50 more manhours to complete this activity therefore this activity is 50% complete.

 

asnwer #2

you can make the activity a resource dependent type of activity these activities are scheduled to work according to the resources’ calendars rather than the activity’s calendar. The activity’s duration is determined by the availability of resources to work on the activity. You should use a resource dependent type of activity when multiple resources are assigned to the same activity. So the resource will drive the activity status.

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts