Dear All,
After updating my program i found the earned value and the actual units for "some" activities equal to zero ( didnot update),
so i had to fix it manually on excel and import on p6, i'm usining duration %.
Any idea what could be the reason? and how to fix?
Thanks.
no problem
Thanks Zoltan
the reason is that you are using duration % complete NOT physcial % complete
Thanx Zoltan, I just wanted to know why it doesn't show any values. (the explaination)
to do what ?
Hi,
You can write your data in UDF coulomn, after you import P6. And then Use Global change.
use physical % complete