Road Time Schedule

Dear Planners,

I will be in a new project for road design and construction which is new for me, can you provide me with the main activities for design and construction and how to link bewteen them (sequencing)?

Thanks in advance

Moutaz

Z
Zoltan Palffy 👤 Member for 16 years 10 months

Design

Issue Contract NTP

Layout and Obtain Borings

Prepare FDR

Prepare Geotech Report

Prepare DER

Prepare 25% Highway Plans

Submit 25% Design Package

Review 25% Highway Package

Review Geotech Report

Schedule Design Public Hearing

Conduct Public Hearing

Respond to Comments

Prepare 75% Highway Plans

Submit 75% Design Package

Review 75% Highway Plans

Prepare 100% Highway Plans

Submit 100% Design Package

Review 100% Highway Plans

Prepare PS&E

Submit PS&E

Review PS&E & Submit to CEPO

Advertise

Environmental Permitting

Coordinate Early Environmental Documents

Prepare ENF

Review ENF

Approve ENF

Prepare CE

Approve CE

Prepare Sect. 106 Hist Arch

Review Sect. 106 Hist Arch

Approve Sect. 106

Evaluate Programmatic 4(F) Applicability

Draft Preliminary Programmatic 4(F)

Review Programmatic 4(F)

Approve Programmatic 4(F)

Reqeust MESA Rare species survey

Determine MESA Habitat

Review and File MESA

Approve MESA

Delineate Wetland Resources

Prepare ACOE PGP

Review ACOE PGP

Approve ACOE PGP

Submit WQC

Review and File WQC

Approve WQC

Prepare 25% HazMat Research

Review 25% HazMat Research

Review 75% HazMat Research

Issue Environmental Clearance

ROW

Prepare Prelim ROW Plans

Review and Accept Prelim ROW Plans

Hold Town Meeting

Perform Title Work

Contact Property Owners

Perform Appraisals

Prepare Layout Taking Plans & Instrument (TPI)

Review & Accept Layout TPI

Approve Acquisition, Record and File

Submit Community Compliance Package

Review Community Compliance Package

Issue Certificate

M
moutaz aldeib 👤 Member for 22 years 5 months

Thanks Zoltan,

I mean the main design and construction activities for road constructing.

Best

Z
Zoltan Palffy 👤 Member for 16 years 10 months

Preliminary Field Review Report 

Draft News Release

Prepare for Public Involvement

Distribute Survey Information and Request Design Input 

Control Diagram

Typical Sections

Preliminary plan and profile sheets

Preliminary cross sections 

Establish Alignment & Grade

Prepare Scope of Work Report 

Approve Scope of Work 

Prepare Plans for Plan-in-Hand 

Plan-in-Hand Inspection

Provide Construction Limits to R/W Agency 

Design Miscellaneous Features 

Final Plan Review 

Final Plan Updates and Revisions

Check Plans 

Transmit to Contract Plans 

Road Design Site Evaluation

Design Conceptual Plan

Final Mitigation Plan Development 

Issue bids

review bids

award contract

contractor create construction schedule 

 

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts