Hello
I am wanting to set marker points/milestones along the activity line for procurement [[wysiwyg_imageupload::]]for a high level tender schedule in P6. I have done this before some time ago using dates in the user defined fields to capture the dates (ie: Bid Submission / PO Award / Delivery).
Has anyone else done this before and can offer some assistance?
Thanks
why not create a unique code for the activities that you want to show then assign the code value to each of theses activities then filter for that code