Level Of Effort Spurious Actuals ?

Can anyone shed some light on why occasionaly and randmly all my summary level of effort tasks show an actual start and an actual finish when they have no physical progress  recorded and none of the tasks they are spanning have actuals?  They all have logic of SS and FF so the point that level of effort tasks will show 100% complete if no logic is applied does not count in this instance.  Any advice help would be appreciated.

A
Alastair Morrison 👤 Member for 19 years 4 months

Exactly !!!  Make surte the "ignore other projects " box is   unticked in the scheduleing options

Z
Zoltan Palffy 👤 Member for 16 years 11 months

so the lesson learned here was to remember not to ignore relationships to and from other porjects

A
Alastair Morrison 👤 Member for 19 years 4 months

This would appear to be my issue one of the planners must have the "ignore relationships to and from other projects" ticked in there schedule options.

Therefore when they schedule their Lv3 plan with the summary / control plan Primavera does as it's told and ignores the links and the LoE's activities which have drivers from the other Lv3's go to zero remaining duration. 

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts