Level activities with small duration (<1 hour)

Hi,

I have this situation:

Duration activities are  1 hour in level activities to share (corect) resources

capture1.png

 

Duration activities are  30 min ; in level activities to share resources ; incorect results.

capture2.png

P6 dont level activities with small duration (minutes) ?

Thanks

R
Rafael Davila 👤 Member for 22 years 3 months

Any software should handle resource leveling down to the minimum duration you can assign to an activity, you got to be missing something. I do not use P6 but see it can display 1/100 minutes.

Try checking Activity Duration Type.

http://www.qsarticle.com/activity-duration-types-in-primavera-project-p…

If the above does not works then I suggest trying with the following simple schedule from scratch and see what happens. One resource A and one resource B units are available. There are no activity links, very simple. Even if one second activities it should do it.

ShortDurations photo ShortDurations_zpsrbh6isul.jpg

Good luck.

M
Mahisha M. Reno 👤 Member for 11 years

Hi,

 

You might want to look at the "Max unit / time" on the resource which assigned to those activities.

See if the max unit/time still allow the resource to be executed on the same hour or not..

 

Regard,

MRE

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts