Hi,
I have a question, In my program the total float for total project is -587 days, but in my activities the maximum that I have is -125, I recently change from P6 V. 8.2 to 8.4.
Regards
Hi,
I have a question, In my program the total float for total project is -587 days, but in my activities the maximum that I have is -125, I recently change from P6 V. 8.2 to 8.4.
Regards
make sure that you filter for all activities
and as Rafael mentioned see if you have any external links from other projects tied to your activities. If you do there should be an asterisk in the right hand side of the finish date column
-587<-125<0<1
Total Project float -587 is less than the minimum activity float -125 is what I believe you mean, that other activity float values are greater, something like -100, -50, 0 or 10.
Good luck