i am trying to see predecessor and successor of activties as column. but i do not see columns for that . how can i add predecesor and successor columns?
they dont exist? if so why? it seems pretty basic, even in ms project they exist
i am trying to see predecessor and successor of activties as column. but i do not see columns for that . how can i add predecesor and successor columns?
they dont exist? if so why? it seems pretty basic, even in ms project they exist
thanks i saw.
they are there
Ahmet,
Under the List Category.
Regards,