Resource and Cost Loading

Hi All,

I am new in Primavera P6 however i am now experience in Preparing/updating schedules in P6 w/o resource and cost loading. Now i am in next step to learn these as well.

Can anybody help to share the stuff/material for easy learning for resource and cost loading and controlling in P6.

Thanks in advance to all.

Regards,

Muhammad

Z
Zoltan Palffy 👤 Member for 16 years 10 months

create resources

assign resources to each activity

then assign the manhours and dollars assoiciated with each activity pe resource

view show on bottom resource usage profile

thats about it 